CR in numbers: Project delivery

CR IN NUMBERS10 / 10

Capital-project status · Q4 2025

Completed projects and unfinished work.

63 / 115
complete or substantially complete23 in progress · 27 delayed · 2 proposed cancellations
One square = one project · 115 projects
63Complete / substantially complete
23In progress
27Delayed
2Proposed for cancellation

I want residents to know why a project is delayed, what that means for its cost and what happens next.

One square per project, not one dollar. Proposed cancellations are not final decisions.

Sources & exact numbers +

The Q4 2025 Finance report is dated February 23, 2026 and was presented in March. Its categories distinguish complete or substantially complete and in service, underway, delayed, and identified for cancellation. Not every unfinished project is late: some are multi-year. Project-count shares are not comparable to the 21.8% of capital budget spent, since sizes, timing and carry-forwards differ. This is a dated snapshot, not today’s live status.

Sources checked 8 September 2026. These are dated public records, not a live feed.

One square = one project · 115 projects. Capital-project status · Q4 2025.
MeasureProjects
Complete / substantially complete63
In progress23
Delayed27
Proposed for cancellation2
Chart 10 of 10: Project delivery. Completed projects and unfinished work.