CR in numbers: Project delivery

CR IN NUMBERS10 / 10

Capital-project status · Q4 2025

I want the unfinished work in view.

63 / 115
complete or substantially complete23 in progress · 27 delayed · 2 proposed cancellations
One square = one project · 115 projects
63Complete / substantially complete
23In progress
27Delayed
2Proposed for cancellation

I give credit for work delivered. I also want a clear explanation and next step for every delayed project.

I give each project one square, not one dollar. I do not call proposed cancellations final decisions.

My sources & exact numbers +

I use the Q4 2025 Finance report, dated February 23, 2026 and presented in March. I distinguish complete or substantially complete and in service, underway, delayed, and identified for cancellation. I do not assume every unfinished project is late: some are multi-year. I do not compare the count share with the 21.8% of capital budget spent, because sizes, timing and carry-forwards differ. I label this a dated snapshot, not today’s live status.

I checked these sources on 8 September 2026. I am showing dated public records, not a live feed.

One square = one project · 115 projects. Capital-project status · Q4 2025.
MeasureProjects
Complete / substantially complete63
In progress23
Delayed27
Proposed for cancellation2
Chart 10 of 10: Project delivery. I want the unfinished work in view.