CR in numbers: Project delivery
Capital-project status · Q4 2025
I want the unfinished work in view.
I give credit for work delivered. I also want a clear explanation and next step for every delayed project.
I give each project one square, not one dollar. I do not call proposed cancellations final decisions.
My sources & exact numbers +
I use the Q4 2025 Finance report, dated February 23, 2026 and presented in March. I distinguish complete or substantially complete and in service, underway, delayed, and identified for cancellation. I do not assume every unfinished project is late: some are multi-year. I do not compare the count share with the 21.8% of capital budget spent, because sizes, timing and carry-forwards differ. I label this a dated snapshot, not today’s live status.
I checked these sources on 8 September 2026. I am showing dated public records, not a live feed.
| Measure | Projects |
|---|---|
| Complete / substantially complete | 63 |
| In progress | 23 |
| Delayed | 27 |
| Proposed for cancellation | 2 |